Construction of a gas pipeline in Pakistan

The 1,100 KM Karachi-Lahore gas pipeline with
a throughput of 12.3 blnM3 of gas per year

The 1,100 KM Karachi-lahore gas pipeline with a throughput of 12.3 blnM3 of gas per year

Project summary

  • The project is implemented in line with an intergovernmental agreement between Russia and Pakistan. RT-GR nominated as the project developer from the Russian side.
  • A BOOT (build – own – operate – transfer) contract for 25 years.
  • Indicative cost – $2.5 bln.

Investment benefits

  • Investment returns through the gas transmission tariff (a take-or-pay rate in $);
  • A guarantee from the Government of Pakistan for Project;
  • A strategically important project for Pakistan: energy shortages limit the country’s economic growth

Power consumption in Pakistan

RT-GR_AR-2015-RUS-10.png
1

BILLION DOLLARS

the volume of assets under management

15

unit

the number of portfolio companies

18

BILLION DOLLARS

the total investments
in projects

5

branches


in focus

Project highlights

Logistics
RegasifidLnG from marine terminals in the south of the country is
transported to power stations and industrial customers in the north.
Length 1100 km
Capacity
12.3 blnm3 per annum.
Implementation ap proach Three stages: Stage 1 – the pipeline; Stage 2 – the fist group of com-
pressor stations; Stage 3 – full capacity operation.

Our mission

- Be to an integrator of smart business solutions for the purpose of increase of investment appeal of assets for the benefit of the Rostec Corporation and the state.